MNRE Clarifies ALMM Rules for Government Captive Solar Projects

The Ministry has now clarified that government projects under Net Metering, Behind-the-Meter, and Open Access mechanisms that are awarded through bidding are exempt from using solar PV cells from ALMM List-II.

This exemption applies only if the last date for bid submission is on or before August 31, 2025. For such projects, compliance with ALMM will be limited to using only solar PV modules from ALMM List-I.

It is important to note that this exemption does not provide any relaxation from domestic content requirements for government projects under schemes or programs where the use of domestically manufactured solar PV cells and modules is already mandated.