CERC Notifies Escalation Rates for Imported Coal Power Procurement in April 2025

The notification, dated May 5, 2025 and published on May 19, 2025, is issued in accordance with Clause 5.6 (vi) of the MOP guidelines dated January 19th, 2005, as amended, along with subsequent MOP communications and resolutions related to power procurement from thermal power stations using imported coal.

The CERC has specified the following monthly escalation rates for payment in April 2025:

Sr. No.DescriptionMonthly Escalation Rates for Payment
1Escalation rate for imported coal(-)0.72%
2Escalation rate for transportation of imported coal(-)7.93%
3Escalation rate for inland handling of imported coal(-)0.41%

These negative escalation rates indicate a decrease in the cost components related to imported coal for power procurement during April 2025, as per the established guidelines and Power Purchase Agreements (PPAs). This could translate to a slight reduction in the power purchase costs for distribution licensees during this period.